BHEL is the largest engineering and manufacturing enterprise in India in the energy-related/infrastructure sector, today. BHEL was established more than 54 years ago, ushering in the indigenous Heavy Electrical Equipment industry in India - a dream that has been more than realized with a well-recognized track record of performance. The company has been earning profits continuously since 1971-72 and paying dividends since 1976-77

News

  • 3X90.3 MW RUPPL DMD Dahej – Unit#1 Condenser successfully placed on foundation on 20/05/2015 at 15:30 hrsPhoto
  • 4x93.1 MW RUPPL HMD Hazira Unit#1: Generator Stator successfully placed on position at 19:00 hrs on 19/05/2015 using strand jack system
  • 3X90.3 MW RUPPL DMD Dahej – Unit#2 Generator lifting and placement successfully achieved on 07/04/2015 at 1700 hrs
  • Foundation Stone Laying ceremony at 4X270 MW Bhadradri TPS, TSGENCO Manuguru in presence of Hon’ble Chief Minister, Telangana, CMD TSGENCO, CMD BHEL, Director (Power) and ED (PSWR) on 28/03/2015Photo
  • BHEL received an order of Rs. 5044 Crore for 4x270 MW Bhadradri EPC Project: Zero Date – 21/03/2015
  • 2X20 MW Tendaho Sugar Factory Phase#I – Unit#2 synchronized successfully at 23:58 hrs local time on 30/03/2015
  • 2X500 MW Chandrapur Project - Unit#8 achieved full load at 18:16 hrs on 29/03/2015
  • 2X600 MW DB Power - Unit#2 achieved full load at 20:15 hrs on 24/03/2015
  • 2X20 MW Tendaho Sugar Factory Phase#I - Unit-2 STG put on barring gear successfully at 17:30 hrs local time on 24/03/2015
  • 3X90.3 MW RUPPL DMD Dahej – Unit#1 Generator lifted successfully on 20/03/2015 at 1530 hrs
  • IOCL Vadodara - Hon'ble Chairman, IOCL visited site on 17/03/2015Photo
  • IOCL Vadodara – Unit#6 GTG & HRSG commissioning completed on 10/03/2015. Customer issued Commissioning CertificateCertificate
  • Hon'ble Chairman and Managing Director of KRIBHCO visited KRIBHCO Hazira site on 19/01/2015Photo
  • 2X800 MW NTPC Lara (ESP) - Erection of ESP Unit #1 started on 08/12/2014 in the presence of GM BHEL (project-VIII) and GM NTPC Lara
  • OPGS Kutch-Unit#2 Boiler light-up achieved at 12:00 hrs on 29/11/2014. Unit#2 BLU has been achieved in subsequent month(only 52 days difference) of Unit#1 as compared to contractual gap of three months between two unitsPhoto
  • 2X20 MW Tendaho Sugar Factory Ph#I – Unit#2 Oil flushing started on 06/11/2014 at 1600 hrs
  • Koniambo 2X135 MW: Unit#2 synchronized on 30/08/2014 at 1730 hrs as per New Caledonia Standard Time
  • 2X20 MW Tendaho Sugar Factory Ph#1-Unit#1: Synchronization with DG Set successfully achieved at 0100 hrs (Ethiopian standard time) on 21/08/2014
  • ED/PSWR visited NTPC, Lara site on 04/08/2014Photo
  • 2X20 MW Tendaho Sugar Factory Ph#I Unit#1 STG put on barring gear successfully at 18:30 hrs on 10/07/2014
  • NTPC Vindhyachal Unit#13 created a new benchmark of 20407 MT erection in Boiler Unit#13 within 1 year
  • BHEL wins Gold Trophy of "SCOPE Meritorious Award for Best Practices in Human Resource Management" for the year 2010-11.Photo