BHEL is the largest engineering and manufacturing enterprise in India in the energy-related/infrastructure sector, today. BHEL was established more than 54 years ago, ushering in the indigenous Heavy Electrical Equipment industry in India - a dream that has been more than realized with a well-recognized track record of performance. The company has been earning profits continuously since 1971-72 and paying dividends since 1976-77

News

  • Associates’ Meet 2012- Moving Ahead with Performance Synopsis  Photos
  • 2X20 MW Tendaho Sugar Factory Ph#I Unit#1 STG put on barring gear successfully at 18:30 hrs on 10/07/2014
  • NTPC Vindhyachal Unit#13 created a new benchmark of 20407 MT erection in Boiler Unit#13 within 1 year
  • 2X135 MW Koniambo Site-Unit-II Safety Valve floating completed on 20/06/2014
  • 2X20 MW Tendaho Sugar Factory Ph#I-Unit#1 Oil flushing completed on 06/06/2014
  • 1X600 MW Jhabua Power-Turbine lube oil flushing started on 17/05/2014 at 15:30 hrs
  • 2X20 MW Tendaho Project, Ethiopia Unit#1 Oil Flushing started at 18:00 hrs (Ethiopian Std Time) on 10/05/2014
  • RSP SAIL Rourkela Project Turbo Blower#3-72 Hrs Trial run completed successfully on 24/04/2014
  • RSP SAIL Rourkela Project - Turbo Blower#3 Surge Test completed successfully on 15/04/2014
  • 2X500 MW Chandrapur Project - Unit#9 Generator Stator lifting successfully completed on 15/04/2014 at 20:28 hrsPhoto
  • 1X600 MW KWPCL Avantha Power-Unit#1 Full Load achieved successfully on 31/03/2014 at 14:48 hrs
  • 2X600 MW D B Power: Unit#2 synchronised at 05:04 hrs on 30/03/2014. This is achieved within 96 days from BLU
  • 2x12 MW Finchaa – STG#1 successfully synchronized with 11 KV Bus System on 11/03/2014 at 15:00 hrs Ethiopian Standard Time (EST) and put on Load
  • 2X600 MW DB Power : Unit#1 achieved full load at 07:04 hrs on 23/02/2014. This is the 1st 600 MW set achieving Full Load in PSWR
  • 5X270 MW IndiaBulls Nasik Phase-1: Unit#1 achieved full load on 25/02/2014 at 01:58 hrs
  • JPL Raigarh 4X600 MW-Unit#3 (2nd Unit) synchronized on 22/02/2014 at 1631 hrs
  • 5X270 MW India Bulls Amravati: Unit#2 achieved full load at 21:02 hrs on 17/02/2014Photo
  • 5x270 MW India Bulls Amravati Unit#2 synchronised with coal at 17:09 hrs on 01/02/2014
  • 2X500 MW NTPC Mauda Unit#1-Trial Run successfully declared completed on 28/01/2014
  • Director (Power) and ED/PSWR visited Amravati site on 07/01/2014Photo
  • Sintex Dhule 2X150 MW Project:Boiler Unit#2 Drum lifting completed on 05/01/2014
  • GM NTPC Mauda appreciated BHEL Mauda Team for Achieving Unit#2 Full LoadPhoto
  • BHEL wins Gold Trophy of "SCOPE Meritorious Award for Best Practices in Human Resource Management" for the year 2010-11.Photo